Projects for Bid
North Hills Council of Governments - Sanitary Sewer Rehabilitation
Bid Opening Date: June 28, 2012
Estimate $ n/a
This is a COG-Wide bid to provide sanitary sewer rehabilitation services (CCTV, grouting, spot repair, trenchless technology repair, manhole rehab, etc.) to the municipal members of the North Hills COG.
Bids were received by:
Contrator | Bid Amount |
Cont. A. Grouting | |
Robinson Pipe Cleaning |
$3,090.99 |
State Pipe Services | $4,416.15 |
Cont. B. CIPP |
|
Insight Pipe Contracting |
$3,776.53 |
State Pipe Services |
$6,020.10 |
Cont. C. CCTV & Cleaning |
|
Robinson Pipe Cleaning | $52.85 |
Insight Pipe Contracting | $63.73 |
State Pipe Services |
$84.42 |
Cont. D. Sliplining |
|
State Pipe Services | $8,694.38 |
Cont. Fa Open Cut 8" - 18" | |
State Pipe Services | $40,972.20 |
Fleming-Walker, Inc. | $43,311.30 |
Cont. Fb Open Cut 21" - 36" | |
State Pipe Services | $61,000.00 |
Fleming-Walker, Inc. | $76,265.70 |
Cont. F-1 Open Cut (Hr/Day) | |
Fleming-Walker, Inc. | $6,500/Day - $650/Hr |
State Pipe Services | $8,500/Day - $200/Hr |
Cont. F-2 Open Cut Pipe Replace/Install | |
State Pipe Services | $26,999.00 |
Fleming-Walker, Inc. | $31,615.00 |
Cont. G Trenchless Sect. Repairs | |
State Pipe Services | $35,600.00 |
Robinson Pipe Cleaning | $41,305.00 |
Insight Pipe Contracting | $102,068.40 |
Cont. H Chemical Root Control |
|
Robinson Pipe Cleaning | $81.84 |
Cont. I Cured In Place UV Cure | No bids received |
Technical questions may be submitted to the Primary Engineer, Bob Robinson at 724-935-3090 x. 112 or the Secondary Engineer, Kevin Creagh at 412-486-9700 x. 230.
Millvale Borough
NSP Demoliton of Ten Properties
Bid Opening Date: August 4, 2010
Estimate $85,000 - 95,000
Notice is hereby given that the specifications and proposal forms are available from the North Hills Council of Governments (NGCOG) for the above mentioned project.
A nonrefundable fee of Forty-five Dollars ($45), payable in advance, will be charged for each set of the above specification if it is to be mailed or Fifty Dollars ($50) if it is to be picked up at the NGCOG offices at 300 Wetzel Road, Suite 201, Glenshaw, PA between the hours of 9:00 am and 4:00 pm weekdays. All checks must be made payable to the North Hills Council of Governments. Request specifications and proposal form.
No documents will be distributed within 24 hours of the scheduled receipt of bids.
Bids will be received at the NHCOG office at 300 Wetzel Road, Suite 201, Glenshaw, PA 15116 until 11:00am, prevailing time, on Wednesday, August 4, 2010. All bid proposals will be opened and read at that time at the NHCOG office. The NHCOG reserves the right to reject any and all bids in whole or in part and to waive any informalities.
Bids must be accompanied by a Bid Bond, Cashiers's Check, or Certified Check made payable, without condition, to the North Hills Council of Governments in an amount no less than 10% of the bid. Cash will not be accepted.
Bid Packages were requested by:
Contrator | Bid Amount |
Ken Reilly Contracting | $107,000 |
Belich General Contractor | n/a |
Lutterman Excavating | $81,000 |
Follow up Questions. Please review the FAQs and your bid package before submitting any questions.
View General Frequently Asked Questions
Questions may be submitted to the engineer, Phil Herman, Senate Engineering at 412-826-5454.
Etna Borough
Ganster Street Culvert Repair
Bid Opening Date: July 13, 2010
Estimate $ 85,000+/-
Bid Packages were requested by:
Contrator | Bid Amount |
WM Aiken & Son Excavating | n/a |
Cilenti Construction Co., Inc. | n/a |
Process Contracting Co., Inc. | $35,940.00 |
Mar-Allen Concrete Products, Inc. | $151,220.00 |
Eveready Contracting | n/a |
Michael Facchiano Contracting Inc. | n/a |
CH & D Enterprises Inc. | n/a |
Follow up Questions. Please review the FAQs and your bid package before submitting any questions.
Technical questions may be submitted to the engineer, Don Newman, Buchart-Horn, Inc. at 412-261-5059.
Etna Borough
NSP Demolition: 14 Freeport Street
Bid Opening Date: July 13, 2010
Estimate $ 25,000+/-
Bid Packages were requested by:
Contrator | Bid Amount |
Eveready Contracting | $29,800.00 |
Empire Dismantlement | n/a |
Ford General Industries | n/a |
R & B Contracting | $34,000.00 |
Kaclik Builders LLC | $56,500.00 |
Technical questions may be submitted to the engineer, Don Newman, Buchart-Horn, Inc. at 412-261-5059.
O'Hara Township
Intersection Upgrades - Work of Widening Fox Chapel Road and Delafield Road
Bid Opening Date: July 13, 2010
Estimate $ 700,000+/-
Bid Packages were requested by:
Contrator | Bid Amount |
Pugliano Construction Co., Inc. | $708,624.00 |
Lindy Paving, Inc. | n/a |
Tresco Paving Corporation |
n/a |
A. Folino Construction, Inc. | $772,793.85 |
Frank J. Zottola Construction, Inc. | $767,777.70 |
Michael Facchiano | na |
Joseph Vaccarello, Jr., Inc. | $812,471.10 |
Astco Construction, Inc. | $745,955.45 |
Zavala Inc. | n/a |
Power Contracting Company | n/a |
M. Facchiano | $825,991.85 |
Technical questions may be submitted to the engineer, Chuck Steinert, (O'Hara Twp.) at 412-782-1400 Ex.t. 217.