Millvale Borough
Riverfront Park Lighting
Bid Opening Date:  March 15, 2012
Estimate $33,000 - $36,000

Bid Packages were requested by:
Contrator Bid Amount  Base / Alternate
Power Contracting Co. $30,574.60 / $38,929.00
CWI - Clean World Industries
No bid
Mann Construction Inc. $77,300 / $84,800
Plavchak Construction Co., Inc. $30,425 / $34,925
iSqFt Plan Room (Reporting Agency) No bid
Schultheis Electric $43,885  / $47,485
Franco Electric $39,360 / $42,290
Pampena Landscaping $56,800 / $65,300
Thompson Electric $29,250 / $32,750

Follow up Questions. Please review the FAQs and your bid package before submitting any questions. Technical questions regarding the bid package may be submitted to the project engineer, Phil Herman, Senate Engineering (412) 826-5454.

Compliance Requirements