Sharpsburg Borough
Water Distribution System Valve Replacement CDBG Yr. 41 7.8 C
Bid Opening Date: September 24, 2015
Estimate $60,000 +/-
This project consists of the replacement of Water Valves within the Borough, including line stops and site restoration.
Bid Packages were requested by:
Contrator | Bid Amount |
R & B Contracting & Excavation | No Bid |
W.D. Wright Contracting Inc. | No Bid |
Soli Construction, Inc. | $73,600.00 |
Follow up Questions. Please review the FAQs and your bid package before submitting any questions. Technical questions regarding the bid package may be submitted to the project engineer Robert Zischkau, Glenn Engineering, Inc. 412-824-5672.